The Redesign Project
The following updates and re-design work was carried out at the Domaine before
the 2002 Harvest.
1. Grape receival area: Reconcreting the receival pit and installation
of a pneumatic
press, destemmer and crusher.
2. Vinification and Storage: Lining of concrete tanks with epoxy resin and installation
of 15 stainless
steel vinification and storage tanks.
3. Temperature Control: Installation of state-of-the-art heating and cooling system.
4. Electricity: All new wiring and circuitry for the whole winery.
5. General Equipment: New pumps, pipe work, stainless steel doors and taps
for epoxy lined vats, barrels and updating of laboratory area.
6. General: Complete cleaning and repainting
CLICK HERE TO SEE THE PICTURES
|